287 Street Bridge Replacement

The City of Maple Ridge is replacing the existing two lane bridge at 287 Street at 123 Avenue. The bridge is 17 metres long across Whonnock Creek and provides service to 13 properties to the north west of the creek. The original bridge was built in 1991 using two used railway boxcars welded together and capped with a concrete deck. This unconventional construction has serviced the area well but is now in need of replacement with a modern bridge design.

The project Tender closed on April 13, 2018 and has been awarded to Seismic 2000 Construction Ltd.

The City has developed an innovative approach to minimize impacts to the neighbourhood. A new prefabricated girder bridge with concrete deck is being constructed and the old bridge will be lifted out and replaced with the new one. Single lane alternating traffic will be in effect. The Fire Department will be on-site during the structure replacement. The new bridge will be in service early in the new year.